The last couple of years we mainly worked on the engine of the datacenter. Adding an extra UPS, a couple of gen sets, a lot of cooling units, training our staff and adding new colocation areas.

All those relate to the inside of the heart of the datacenter... our engine to say this metaphoric. So we can bluntly say we have been tuning our engine so it runs like a charm.

So in 2019 another project was launched. Executing a revamp op the Antwerp Datacenter looks of the building. Making sure the body of our car reflects our roaring Ferrari engine on the inside...

Plan AntwerpDC

Revamp op the Antwerp Datacenter building

Friday 5th April 2019

Antwerp Data Connectivity Day !

Friday 8th March 2019

Gartner predicts: European datacenters may double in 5 years

Tuesday 15th January 2019

Antwerp and Brussels Datacenter not in outage plan

Saturday 10th November 2018

Our renewed ISAE3401 Type I certification

Monday 15th October 2018

Our team is expanding

Wednesday 5th September 2018

Antwerp Datacenter extra cooling system

Friday 10th August 2018

Antwerp Datacenter Power room and Carrier room new cooling.

Tuesday 12th June 2018

Syntra visits Antwerp Datacenter

Wednesday 2nd May 2018

Start of DataCenter United Blog

Wednesday 4th April 2018

Team expanding

Thursday 15th March 2018

New Carrier Arcadiz Networks

Tuesday 4th July 2017

Major Belgian carrier Orange joins Antwerp DC

Tuesday 16th May 2017

Syntra visits Antwerp Datacenter

Thursday 27th April 2017

Installation of Extra UPS and battery string

Thursday 16th March 2017

PCI DSS certification

Thursday 12th January 2017

ISO27001:2013 certification

Tuesday 7th June 2016

CDCP certifications staff

Monday 25th April 2016

Team expanding

Sunday 14th February 2016

ISAE3402 Certifications

Thursday 14th January 2016

New team member

Tuesday 20th December 2016

New genset installed

Tuesday 13th December 2016

Team expands

Sunday 13th November 2016

Our team is expanding ...

Wednesday 8th October 2014

Antwerp DC offers guided tour to VOKA members

Tuesday 1st April 2014

Offering Twin Colocation Services

Wednesday 22nd January 2014

Antwerp DC becomes The Green Grid member.

Wednesday 30th October 2013

Antwerp DC is a code of conduct participant.

Sunday 1st September 2013

ISO/IEC 27001:2005

Monday 12th August 2013

Antwerp DC takes over AXS Datacenter

Monday 1st October 2012

New coolunit installed

Thursday 10th May 2012

Construction of Node B started

Friday 16th September 2011

Opening event

Thursday 16th December 2010

Node C.1 completed !

Monday 15th November 2010

Construction on shedule

Tuesday 28th September 2010

Datacenter construction started

Monday 6th September 2010